Planning DAG & Critical Path Scheduling

M31A models autonomous software engineering as a dependency-aware Directed Acyclic Graph (DAG) of discrete tasks.

DAG Representation & Critical Path Method​

Located in src/dag/:

  • Nodes: Task entities with explicit inputs, outputs, required capabilities, and verification strategies.
  • Edges: Dependency relationships (depends_on).
  • Critical Path Method (cpm.rs): Calculates earliest start times, latest completion times, and identifies bottleneck tasks along the critical path to optimize parallel execution.

Cycle Detection & Validation​

Before materializing a DAG into SQLite, src/dag/validator.rs validates:

  1. Acyclicity: Tarjan's strongly connected components algorithm ensures no cyclic deadlocks exist.
  2. Capability Satisfaction: Verifies that required capabilities (e.g. fs.write, process.exec) are permitted under the active policy.
  3. Verification Feasibility: Confirms that every mutating task specifies an executable verification strategy.